Stage view shows almost done when there is a long way to go

      Stage view shows as 'Almost done' eventhough there is quite a ways to go. Almost done should be ideally shown when only a couple of minutes are remaining, yeah?

          [JENKINS-39188] Stage view shows almost done when there is a long way to go

          Sam Van Oort added a comment -

          samkr Can you provide information to reproduce this, in a case where Stage View has enough information to make a reasonable estimate?

          Sam Van Oort added a comment - samkr Can you provide information to reproduce this, in a case where Stage View has enough information to make a reasonable estimate?

          Sam Krishna added a comment -

          Well, looks like its starting off with 'Almost complete' by default. I just created 3 empty stage blocks with nothing but sleep 600 in them and right off the bat, its showing 'Almost complete'.

          I upgraded my Jenkins recently and cannot confirm what used to be the correct behaviour before. I apologize if I'm wrong, but from what I can remember, in 2.11 jenkins and before, it would show just a progress bar and as it neared the end...it would show 'almost complete'.

          Sam Krishna added a comment - Well, looks like its starting off with 'Almost complete' by default. I just created 3 empty stage blocks with nothing but sleep 600 in them and right off the bat, its showing 'Almost complete'. I upgraded my Jenkins recently and cannot confirm what used to be the correct behaviour before. I apologize if I'm wrong, but from what I can remember, in 2.11 jenkins and before, it would show just a progress bar and as it neared the end...it would show 'almost complete'.

          xonq nopp added a comment -

          Same here... All my pipelines are showing "almost complete" all the time, even if there still are stages which are known to last for hours after the current stage...

          xonq nopp added a comment - Same here... All my pipelines are showing "almost complete" all the time, even if there still are stages which are known to last for hours after the current stage...

          Simon Michaud added a comment -

          At least remove it if you won't fix it, it is useless.

          Simon Michaud added a comment - At least remove it if you won't fix it, it is useless.

            Unassigned Unassigned
            samkr Sam Krishna
            Votes:
            8 Vote for this issue
            Watchers:
            13 Start watching this issue

              Created:
              Updated: