      Job A starts job B, C, D and E. Additionally, the jobs C and D are starting each other more jobs e.g. C1, C2, D1 and D2. The joined job F should start when all ends (in this scenario: B, C1, C2, D1, D2 and E) are finished.

      Maybe this can be achieved by a text box in which the jobs which needs to finish first can be entered if the multiple downstream levels isn't supporting this.

          [JENKINS-9946] join should be able to wait for all downstream jobs

          robsimon added a comment -

          robsimon added a comment - see: https://issues.jenkins-ci.org/browse/JENKINS-11274

          mdonohue added a comment -

          JENKINS-11274 appears better thought out. Closing this as a duplicate.

          mdonohue added a comment - JENKINS-11274 appears better thought out. Closing this as a duplicate.