Uploaded image for project: 'Jenkins'
  1. Jenkins
  2. JENKINS-9946

join should be able to wait for all downstream jobs

XMLWordPrintable

    • Icon: New Feature New Feature
    • Resolution: Duplicate
    • Icon: Major Major
    • join-plugin
    • None
    • Hudson v1.377, Win Server 2003 R2 x64 SP2, Join v1.9, Parametrized trigger v2.7

      Job A starts job B, C, D and E. Additionally, the jobs C and D are starting each other more jobs e.g. C1, C2, D1 and D2. The joined job F should start when all ends (in this scenario: B, C1, C2, D1, D2 and E) are finished.

      Maybe this can be achieved by a text box in which the jobs which needs to finish first can be entered if the multiple downstream levels isn't supporting this.

            mdonohue mdonohue
            robsimon robsimon
            Votes:
            4 Vote for this issue
            Watchers:
            4 Start watching this issue

              Created:
              Updated:
              Resolved: